Volume Generated:285 Tons removed for a 100% diversion rate
Scope
Coordinate with City of Half Moon Bay and Coastal Commission to obtain beach access for crews and heavy equipment.
Coordinate with AECOM and Environmentalists to develop a safe and efficient work plan.
Coordinate with Ritz Carlton and HMB Golf Links to establish ingress/egress to the job site.
Obtain $35,000,000.00 project-specific GL policy from surety company, prior to commencement.
Install and maintain (1) 600′ construction road, starting at the end of Miramontes Point, finishing at the bluff edge. The road consisted of post-driven chainlink fencing with privacy mesh and 1.5″ steel plating.
Remove and dispose of exposed piers and grade beams.
Demobilize crane and equipment and disassemble construction road.