- Disconnect and safe-off all utilities.
- Decommission (4) HVAC units on the roof and recycle.
- Cut and separate roof lines from perimeter walls that are to remain.
- Demolish 5,500 SF of the structure down to the slab.
- Scrape and grind floor treatments and prep slab for (n) finishes.
- Install tilt-up bracing on perimeter walls upon completion.